Leag builds huge battery storage facility at Boxberg site

Leag builds huge battery storage facility at Boxberg site
The "GigaBattery Boxberg 400" is to be built on the site where the cooling towers of the old power plant were blown up a year ago (archive photo) / Photo: Robert Michael/dpa
From: DieSachsen News
Leag is building a huge electricity storage facility in Boxberg, Saxony, together with a Chinese energy storage provider and Siemens Energy. The facility is intended to compensate for fluctuations in renewable energies.

The energy group Leag wants to press ahead with the construction of large battery storage facilities in eastern Germany. The subsidiary Leag Clean Power has signed a supply and construction contract for the planned giga-battery storage facility at the Boxberg power plant site in Saxony (Görlitz district), the Group announced in Cottbus. The partner is the German subsidiary of the Chinese energy storage provider HyperStrong.

A storage giant is being built where cooling towers once stood

The "GigaBattery Boxberg 400" is to be built on an area of around six hectares where the cooling towers of the former power plant were blown up a year ago. A connected load of 400 megawatts and a storage capacity of 1,600 megawatt hours are planned. According to the company, this could cover the electricity consumption of around 640,000 households for four hours. The system is intended to compensate for fluctuations in the feed-in of renewable energies and stabilize the grid.

The giga-battery will be based on lithium iron phosphate storage systems supplied and integrated by HyperStrong. Siemens Energy will be responsible for the gas-insulated switchgear for the connection to the 380-kilovolt grid. According to Leag, Boxberg is the company's second large-scale storage project after Jänschwalde in Brandenburg. Both locations are to become central sites of the planned "GigawattFactory", with which Leag intends to expand its energy storage and renewables portfolio.

More from this category

"Milestone for the energy transition"

Leag CEO Adolf Roesch spoke of a "milestone" for the energy transition and a building block for a secure supply. HyperStrong CEO Jianhui Zhang called the project an important step in his company's European strategy.

On Tuesday, the EU Commission approved state aid of up to 1.75 billion euros for Leag. This is intended to compensate the company for the statutory early phase-out of lignite - including for recultivation and social costs.

Copyright 2025, dpa (www.dpa.de). All rights reserved

The translations are automated with the help of AI. We look forward to your feedback and your help in improving our multilingual service. Write to us at: language@diesachsen.com.
Sachsen News
Article from

Sachsen News

Sachsen News is responsible for the content itself. The platform's code of conduct applies. The platform checks and treats content in accordance with the legal requirements, in particular the NetzDG.

Social Media