Bridge Test in Dresden a Success—No New Damage

Bridge Test in Dresden a Success—No New Damage
The stress test began on Monday evening. (File photo) / Photo: Katharina Kausche/dpa
From: DieSachsen News
The load test on Budapester Straße in Dresden was completed without causing any new damage. The city explains what the next steps are for the bridge.

The load test on the central Dresden bridge on Budapester Straße has been successfully completed. “The experts are very satisfied with the measurements,” the state capital announced. According to the report, there was no new damage or broken tension cables on the structure. The reserve time slot scheduled for the evening as a safety buffer is no longer needed.

On Monday night and Tuesday night, four heavy-duty vehicles with increasing weights of up to 326 metric tons drove over the prestressed concrete bridge—which is largely closed due to numerous broken tension cables—as part of the test. Sensors recorded how the structure behaved under the load to determine its remaining load-bearing capacity. The cost of the test is 900,000 euros.

More from this category

Bridge Could Be Reopened

The next step is to evaluate the collected data. If the results allow it, the bridge could be gradually reopened. The city plans to provide an update as soon as the analysis is complete. The load test will be followed by a planning and optimization process lasting several months to determine the necessary reinforcement measures for the structure. 

Same construction method as the Carolabrücke

A similar test was conducted in Bad Schandau in April 2025. The months-long full closure of the Elbe Bridge there was subsequently lifted for vehicles weighing up to 7.5 metric tons.

The two bridges in Dresden and Bad Schandau were built using the same construction method as the partially collapsed Carolabrücke in Dresden. Because they were built using Hennigsdorf prestressing steel, they are considered at risk of so-called stress corrosion cracking, which, according to expert reports, caused the collapse of the Carolabrücke in September 2024.

Closure Due to Imminent Collapse

Following the collapse, similar bridge structures in Dresden and throughout Saxony were also scrutinized. Due to the damage discovered during this inspection, traffic on the Budapester Straße Bridge was initially restricted in early May and largely brought to a standstill on May 13 due to further signs of damage. The city had supports installed on bridge span C, which was particularly damaged.

Copyright 2026, dpa (www.dpa.de). All rights reserved

The translations are automated with the help of AI. We look forward to your feedback and your help in improving our multilingual service. Write to us at: language@diesachsen.com.
Sachsen News
Article from

Sachsen News

Sachsen News is responsible for the content itself. The platform's code of conduct applies. The platform checks and treats content in accordance with the legal requirements, in particular the NetzDG.

Social Media