Demolition of the Carola Bridge costs 2.5 million euros less

Demolition of the Carola Bridge costs 2.5 million euros less
The demolition of the partially collapsed Carola Bridge took about a year. (Archive image) / Photo: Robert Michael/dpa
From: DieSachsen News
The demolition of the Carola Bridge in Dresden was cheaper than expected. The city saved 2.5 million euros. Nevertheless, the Left Party is urging people to keep an eye on the scale of the costs.

The demolition of Dresden's Carola Bridge cost 29.5 million euros - 2.5 million euros less than initially assumed. This is the result of answers to several questions from André Schollbach, chairman of the Left Party parliamentary group in the city council. Last September, shortly before the work was completed, the city administration had still assumed a total of 32 million euros.

Cost reduction for accompanying measures

The accompanying measures in particular turned out to be cheaper. The item "Immediate measures, status assessments, traffic routing" was initially listed at 5 million euros, but according to information from February 27, the figure is now 3 million euros.

The remaining sum was due for the actual demolition work. The costs for the two bridge sections not directly affected by the collapse were reduced slightly by 500,000 euros to 20.5 million euros. The city had to pay 6 million for the removal of the collapsed section.

Despite the slight decrease, Schollbach warns that the scale of the costs should also be borne in mind for the new construction. "Almost 30 million euros were needed to remove an existing bridge. That is an enormous sum for our city," he said in a statement.

More from this category

Carola Bridge demolition took a year

The Carola Bridge - a prestressed concrete structure from the GDR era - partially collapsed on the night of September 11, 2024. No one was injured. The demolition took around a year. A total of 30,000 tons of concrete, 2,000 tons of steel and more than 25,000 tons of armourstones were moved in the process.

Planning for the new building is currently underway. Four planning offices are working on designs, which they are due to present by mid-May. According to the city's plans, the new bridge should be completed in 2031.

Copyright 2026, dpa (www.dpa.de). All rights reserved

The translations are automated with the help of AI. We look forward to your feedback and your help in improving our multilingual service. Write to us at: language@diesachsen.com.
Sachsen News
Article from

Sachsen News

Sachsen News is responsible for the content itself. The platform's code of conduct applies. The platform checks and treats content in accordance with the legal requirements, in particular the NetzDG.

Social Media