Bad Schandau: Temporary Bridge Over the Tracks on Schedule

Bad Schandau: Temporary Bridge Over the Tracks on Schedule
The temporary bridge is intended to serve as a temporary replacement for the existing structure that crosses the railroad tracks along the B172. / Photo: Robert Michael/dpa
From: Sachsen News
Progress is being made on the temporary solution for the bridge over the railroad tracks in the Saxon border town. Large sections have already been constructed. Traffic is expected to begin flowing in the first quarter of 2027.

Construction of the temporary bridge over the railroad tracks in Bad Schandau is moving forward. The structure is scheduled to be completed in the first quarter of 2027, as announced by the Ministry of Infrastructure. Two of the four sections have been completed on schedule, and work on the third is currently underway. The final section is scheduled to reach the Königstein side on November 30.

“It’s great to see that residents are following this progress week by week and view the momentum of the work positively,” said Bad Schandau Mayor Thomas Kunack, according to a press release, during an on-site visit. “This development makes us optimistic that traffic will be able to flow without traffic lights by early 2027.”

Existing bridge must be demolished

A special inspection of the existing bridge—which runs along the B172 over the railroad tracks and adjoins the Elbe Bridge, which has been closed for months—revealed weaknesses in its load-bearing capacity. It must be demolished in the near future. A new bridge is planned for the long term.

The temporary bridge will serve as a stopgap until the new bridge is completed. “We’re now providing a temporary replacement, after which the old bridge will be taken out of service,” explained Infrastructure Minister Regina Kraushaar (CDU). People in the Upper Elbe Valley must be able to rely on a safe crossing over the Elbe. We know just how important this is, especially for Bad Schandau.

Temporary bridge built nearby and then moved

The steel structure, weighing approximately 630 metric tons and measuring 147 meters in length, is being constructed using the so-called “push-launch” method. In this process, the bridge sections are assembled next to their final position and then moved into place. “Pushing 630 metric tons of steel across seven railroad tracks is both a feat of engineering and precision work,” said Kraushaar.

According to previous estimates, the costs—including maintenance and repairs over the bridge’s service life—amount to approximately 10 million euros. Once the temporary bridge is completed, the old structure will be closed to traffic in 2027 and dismantled. The new bridge will then be built on the same site.

Copyright 2026, dpa (www.dpa.de). All rights reserved